 Moving forward and making progress on the frames.  After installing the side planks for the stem and gripe, I ground them down to the proper angle.  I made a new piece for frame number 1 which was installed recently.  

 


I also installed frame number 3.  

 


Frame number 2 was broken on the starboard side so I replaced that and the part of the frame on the bottom of the boat.   I saved the port side vertical frame with some Smiths Epoxy repair.  

 


Then I installed frame 2 and 2a in one day.  

 



I have one more intermediate frame to install, 3a which has been coated with clear epoxy sealer.